Design-build electrical for a 425,000 SF ground-up manufacturing facility in the Dallas metro. Medium-voltage service, process motor controls, VFD installations, and PLC integration on a 20-month schedule.
Ground-up industrial manufacturing facility supporting continuous process operations across multiple production lines.
340,000 SF production floor, 50,000 SF support and utility space, 35,000 SF office. Building height to 50' clear at production zones.
Oncor Electric Delivery primary service, indoor metal-clad MV switchgear, two 5,000kVA unit substations distributing 480V to plant MCCs. Main-tie-main configuration for concurrent maintainability.
52 production motors from 25HP through 800HP, plus process compressors, chiller plant motors, and material-handling drives.
Preconstruction engagement during schematic design. Coordination with consulting MEP engineer through CD issuance, then GMP execution through energization.
MV switchgear and MCCs released during DD. Process equipment installations sequenced with mechanical and process piping during the final 6 months.
The owner’s operations team was committed to first-product output 22 months from NTP. The electrical scope included long-lead MV switchgear (52-week lead time at the time of release) plus prefabricated MCCs that needed to be on the building shell floor before mechanical and process piping installation began.
We engaged the utility transmission planning group during schematic design, modeled the plant load against the available primary service capacity, and produced a service-entrance design that could be approved early in the project. MV switchgear was released during DD with the owner’s approval, ahead of CD issuance. The eight MCCs were specified, ordered, and prefabricated off-site in a coordinated sequence with the building schedule.
Energization completed on schedule. Production startup began on the contracted date with full plant electrical capacity available. First-product output occurred within the owner’s target window. Closeout including arc-flash labeling, as-built drawings, and operator training delivered to the owner’s operations team during the commissioning phase.
Send us your scope, drawings, and target production date. We’ll come back with pricing and a phased execution plan.